- The Town of Crescent will post construction activity daily via the Town of Crescent Website:
Go to townofcrescent.com.
- A moving single lane of traffic will be open during the daily construction hours.
- Both lanes should be open to traffic before and after daily construction hours.
Crescent Road Construction Schedule
(Note Subject to change due to changing weather conditions.)
September 16-17: Placement of base course material. (NOTE: Traffic Control with one lane open during construction hours and both lanes open after construction hours.)
September 18-20: Road Pulverizing (NOTE: Traffic Control with one lane open during construction hours and both lanes open after construction hours.)
September 24-27: Lane Paving (NOTE: Traffic Control with one lane open during construction hours and both lanes open after construction hours.)
September or October: Shoulder Placement and Shaping (NOTE: Traffic Control with one lane open during construction hours and both lanes open after construction hours.)
If you have any questions, please contact Robb Jensen at crescentchair@townofcrescent.com or 920.602.0561.
Robb W Jensen-Chair